COMMERCIAL & INDUSTRIAL – Demo System Packages

Based on our experience, the roof area for factories or commercial buildings is more than 4000sqft.

Here are the planning matrix for your to choose a right size system for you:
Available Roof Area Installing Capacity Monthly Yield Monthly Saving in S$ Estimate ROI
4,000sqft 48~52kWp 5,800-6,600kWh S$1,800 6.5-7 Years
5,000sqft 60~65kWp 7,250~8,250kWh S$2,250 7.5-7 Years
10,000sqft 120~130kWp 14,500~16,500kWh S$4,500 6.5 Years
20,000sqft 240~260kWp 29,000~33,000kWh S$9,000 6.5 Years
* The planning matrix is just provided for your guidance, and please contact us by 6356 4001 or hyland@hyland.com.sg for further details.

For a commercial project, a project normally takes around 16 weeks, including physical installation, application, submission and approval from related authorities.

1st - 2nd Week Getting the contract signed and confirmation deposit from the customer
3rd - 4th Week Signing the SP application form by Customer for our submission and paper work clear
5th - 6th Week Waiting for progress approval letters from SP Service
7th - 10th Week Carrying out physical installation and waiting for progress approval letters from SP Service
11th - 12th Week Finishing physical installation and waiting for progress approval letters from SP Services
13th - 14th Week Waiting for progress approval letters from SP Service
15th - 16th Week Getting the final approval letter from SP Services and carry out test, inspection and commissioning of the solar system

Any further doubts, please kindly email us to hyland@hyland.com.sg or Call 6356 4001.